NEEM CONTACT MET ONS OP CONTACT US Mapbox Map
Search by business type

Damen Marine Components HQ

H

Poland

P

China

P

Schiedam, the Netherlands

P

The Netherlands

S

Germany

S

Singapore

S V

Cyprus

S

United Kingdom

S

United States

S

Romania

V

China

V

Argentina

V

Australia

V

Croatia

V

Greece

V

India

V

Italy

V

China

V

Norway

V

Singapore

S V

South Korea

V

Sweden

V

Spain

V

Portugal

V

Taiwan

V

Turkey

V

United Arab Emirates

V

United States

V

CONTACT US damenmc NEEM CONTACT MET ONS OP Skip to main content

DMC winch testing procedure

14 June 2021

DMC winch testing procedure

5 min

All our winches are built and tested in our own production facility. Extensive testing is important to guarantee the performance of our winches. But what does such a test involve?

When we have completed the building process of a winch, we place it on our test bench, which has a capacity of 300 tonnes. Then a factory acceptance test (FAT) is performed on 100% load. Testing on 100% load means to determine the maximum operating capacity of a winch and is more important than you think, here’s why:

1. Brakes and clutches are run-in and calibrated

2. Less uncertainties during commissioning and/or trials

3. Faster commissioning process (=cost saving)

The FAT test is carried out under the supervision of a classification society (Lloyds Register, Bureau Veritas, etc.). A final paint job is done after the testing procedure is completed, and after that, the winch is ready for transport and installation on board.